Installation Step 1

The bottom frame is connected with screws to the bottom cross beam and the bottom side cross beam, purlin 8*4 square pipes x9 are connected with screws
Ver detalles

Installation Step 2

Each column is fixed with six sets of hexagon socket bolts, and the column screws do not need to be tightened
Ver detalles

Installation Step 3

Measuring verticality of column with line drop and level
Ver detalles

Installation Step 4

The top frame is connected to the top beam and the top side beam with screws, and the drain hole faces outward.
Ver detalles

Installation Step 6

Install three horizontal square pipes and fix them at the welding angle of the top short beam.
Ver detalles

Installation Step 7

Installation of four columns downspouts
Ver detalles

Installation Step 8

Installation of 8 831 ceiling tiles
Ver detalles

Installation Step 9

Top Spread Rock Wool Roll
Ver detalles

Installation Step 10

Installation of single roof tile
Ver detalles

Installation Step 11

The edge of the ceiling tile shall be hammered with rubber to seal and glue around. It is strictly prohibited to directly trample on the single roof tile during construction. It is necessary to prepare two square pipes to assist construction before stepping on the square pipe.
Ver detalles

Installation Step 12

Installation of cement pressure plate surface with 1.6 plastic floor. Evenly laid.
Ver detalles